Subject: Emergency repairs to 235th Ave. Stormwater Collection system and outfall.

Project Completion Report

As required by Village Code and terms of the Wisconsin Department of Natural Recourses emergency approval dated October 7, 2026, authorizing the removal from Wis. DNR managed wetlands sediment and deteriorated stormwater collection system piping. The following serves as the completion report of the emergency mitigation project.

Project Description

The emergency stormwater collection system mitigation project included the removal of 24 liner feet of 36 inch collapsed, damaged, and deteriorated reinforced concrete pipe, removal of underbrush, compromised trees, and stormwater sediment. The project further included restoration of the mitigated site after the removal of separated out fall pipe, reshaping and regrading the out fall slopes, installing geotextile fabric and installing large rip rap to protect improved site from soil erosion.

The emergency repair project was phase one of a two phase improvement of the stormwater collection system, outfall and drainage basin.

Long-Term Solution

The two-phase project provides a long-term solution for stormwater reliability by improving the integrity of the collection system and out fall, thereby reducing occurrences of regional roadway flooding and frequent obstruction at the collection system out fall. Project improvement has an expected useful service life of up to 25 years. Outfall improvement strengthens efficiency and reliability to convey future stormwater flows.

Compliance with Environmental Requirements

Phase I

Required emergency mitigation measures were approved by the Wis. DNR. The mitigation measures were checked for compliance during field site visits by Village Administrator and Consulting Engineer during mitigation activities.

No archaeological or paleontological resource or any signs of any soil contaminants were encountered during mitigation project, sediment and soils removed under the mitigation project were stored on Village Public Works site for dewatering purposes and before required disposal in a Wisconsin licensed land fill.

Phase II

Which includes improvements to collection system and development of a stormwater sediment control basin. Phase II requires Wis. DNR and Army Corp of Engineer approvals, both of which will be applied for in the near future.

Emergency Mitigation Project Budget

Project Budget and Expenditures

 

Task

Budget

Amount Spent

Tree and underbrush removal

$16,000

$13,000

Emergency mitigation excavation

$12,000

$12,000

Disposal of sediment

$7,000

 

Design

 

$3,700

Construction management

$3,000

$1,560

Administration

$1,000

$925

Wis. DNR Permits

$750

$618

 

$39,750

$31,803

 

 

Sincerely,

Timothy A. Popanda Village Administrator

Attachments:

Before and after photos of site and project plan.