75th Street Construction update for weeks of 9/11/2023 & 9/18/2023:
Stage 4 Construction Work & Traffic Configuration is fully underway. Stage 4 is a long-term stage involving repaving the westbound lanes on the north side of 75th Street. A single lane of traffic in each direction will be maintained on the newly paved eastbound lanes on the south side of 75th Street. Access to all businesses on the north side of the street will be maintained. Any short-term temporary closures will be discussed with the owners.
As a reminder, the project team recommends traveling at 25 mph through the work zone for driver and work zone crew safety and to avoid vehicle damage.
Traffic Updates
• Storm Sewers are currently being installed, which involves short-term closures of side streets
o Friday 9/15: 236th Avenue will be closed from approximately 8:00 AM – 5:00 PM (Another closure MAY be required the morning of Saturday 9/16 if the work isn’t completed by Friday evening)
• 21-Day Closure of STH 75 – North Leg of the intersection with STH 50 & STH 83/Antioch Road
o Beginning Thursday 9/21, the north leg of the STH 50/STH 83/STH 75 intersection will be closed for 21 days. The closure will be from the intersection to the driveways to Brass Ball Mall and Village Plaza – both driveways will REMAIN OPEN. A Get Around Guide to Village Plaza, showing the closure location and local detour routes, is attached. (Dates are subject to change pending weather and scheduling.)
Please refer to the WI 511.gov project website for additional information, and feel free to reach out with any questions. We will send out updates in advance of any major changes during construction. Anyone can sign up to receive these updates by emailing 75thstreetpi@graef-usa.com.